Look-ahead: 30, 60 and 90-day windows from P6

The weekly meeting should start with the work that is about to start, finish or slip. This page filters the P6 schedule to a 30, 60 or 90-day window and flags every activity by status.

Primavera P6Look-aheadWeekly planningPower BI
30/60/90day windows from the data date
4status flags per activity
127activities starting in the example window
27critical activities flagged

The problem

A full P6 schedule has hundreds of activities. Site teams need a short, clear list of what is coming up and what is already at risk, and building that list by hand from P6 layouts every week takes time.

How it works

  1. Pick the window. 30, 60 or 90 days from the data date.
  2. See what is starting and finishing. Counts of activities starting and finishing in the window, plus critical and at-risk counts.
  3. Act on the flags. Each activity is marked critical, at risk, upcoming or on track, with its float and dates.

Walkthrough

Result

The weekly look-ahead is ready on refresh, and the meeting starts with the activities that need action.