Look-ahead: 30, 60 and 90-day windows from P6
The weekly meeting should start with the work that is about to start, finish or slip. This page filters the P6 schedule to a 30, 60 or 90-day window and flags every activity by status.
30/60/90day windows from the data date
4status flags per activity
127activities starting in the example window
27critical activities flagged
The problem
A full P6 schedule has hundreds of activities. Site teams need a short, clear list of what is coming up and what is already at risk, and building that list by hand from P6 layouts every week takes time.
How it works
- Pick the window. 30, 60 or 90 days from the data date.
- See what is starting and finishing. Counts of activities starting and finishing in the window, plus critical and at-risk counts.
- Act on the flags. Each activity is marked critical, at risk, upcoming or on track, with its float and dates.
Walkthrough
Result
The weekly look-ahead is ready on refresh, and the meeting starts with the activities that need action.