DCMA 14-point checklist for P6
All 14 schedule quality checks on one printable page, with the target for each and how to check it in Primavera P6.
A forecast is only as good as the schedule behind it. This one-page checklist lists all 14 DCMA checks, the target for each one, and where to find it in Primavera P6.
| # | Check | Target |
|---|---|---|
| 1 | Logic | ≤ 5% |
| 2 | Leads | 0 |
| 3 | Lags | ≤ 5% |
| 4 | Relationship types | ≥ 90% FS |
| 5 | Hard constraints | ≤ 5% |
| 6 | High float | ≤ 5% |
| 7 | Negative float | 0 |
| 8 | High duration | ≤ 5% |
| 9 | Invalid dates | 0 |
| 10 | Resources | Project-specific |
| 11 | Missed tasks | ≤ 5% |
| 12 | Critical path test | Pass |
| 13 | CPLI | ≥ 0.95 |
| 14 | BEI | ≥ 0.95 |